Completed a turnkey grinder pump station rehabilitation project to improve system reliability, operational visibility, and long-term maintainability. HRA removed aging pumps, controls, and associated equipment and furnished and installed a new control panel, dual 1 HP grinder pumps, float switches with mounting hardware, and upgraded discharge piping connections to the existing gravity sewer system. The project included control panel design, electrical installation, instrumentation integration, alarm configuration, and SCADA connectivity to provide remote monitoring and rapid notification of abnormal operating conditions. Following installation, HRA performed startup, testing, commissioning and operator support resulting in a fully operational and modernized pumping system